| Power Station |
Capacity (MW) |
Present Status / Progress |
Chibro
|
4x60=240
|
Consultants short-listed on the basis of Global EOI, RFP document approved by KfW & sent to the consultants for feasibility studies and DPR etc. Pre-bid meeting held, Technical Bids opened & evaluated. Financial bids opened and being evaluated.
|
Khodri
|
4x30=120
|
Consultants short-listed on the basis of Global EOI, RFP document approved by KfW & sent to the consultants for feasibility studies and DPR etc. Pre-bid meeting held, Technical Bids opened & evaluated. Financial bids opened and being evaluated.
|
Chilla
|
4x36=144
|
SNC Lavalin has prepared DPR for Phase 1 (Study) as per GoU-CCC Agreement
|
Mohd.
Pur
|
3x3.1=9.3
|
In house
'Revised DPR' for M&U has been prepared. Arrangement of loan under REC funding is under progress |
Galogi
|
2x1+2x0.5=3
|
Fresh DPR being prepared, Penstock replacement being planned in the first stage, specifications for other works are being finalized.
|
Tiloth
|
3x30=90
|
Consultants short-listed on the basis of Global EOI, RFP document approved by KfW & sent to the consultants for feasibility studies and DPR etc. Pre-bid meeting held, Technical Bids opened & evaluated. Financial bids opened and being evaluated.
|
Pathri
|
3x6.8=20.4
|
In house
'Revised DPR' for M&U has been prepared. Arrangement of loan under REC funding is under progress
|
Khatima
|
3x13.8=41.4
|
RLA study report for E&M works received, Project planned under EFES route. RFQ invited.
|
Dhakrani
|
3x11.25=33.75
|
Consultants short-listed on the basis of Global EOI, RFP document approved by KfW & sent to the consultants for feasibility studies and DPR etc. Pre-bid meeting held, Technical Bids opened & evaluated. Financial bids opened and being evaluated.
|
Dhalipur
|
3x17=51
|
Consultants short-listed on the basis of Global EOI, RFP document approved by KfW & sent to the consultants for feasibility studies and DPR etc. Pre-bid meeting held, Technical Bids opened & evaluated. Financial bids opened and being evaluated.
|
Kulhal
|
3x10=30
|
Consultants short-listed on the basis of Global EOI, RFP document approved by KfW & sent to the consultants for feasibility studies and DPR etc. Pre-bid meeting held, Technical Bids opened & evaluated. Financial bids opened and being evaluated.
|
Ramganga
|
3x66=198
|
DPR for M&U works prepared by UJVNL and being finalized
|