Home


THE CHALLENGE AND STATUS OF MANERI BHALI STAGE-II HYDROELECTRIC PROJECT (4X76 MW)

Background

Maneri Bhali Stage-II Hydroelectric Project is a Run-of-River(ROR) scheme under construction on river Bhagirathi, in District Uttarkashi (Uttaranchal). The project, is located near the famous city of Uttarkashi and is on the downstream of the existing UJVNL's Tiloth Hydro Power Project. The project site is approximately 150 kms. from Rishikesh, lies between the tailracechannel of Maneri Bhali Stage-I project and the reservoir of Tehri project. 
The project preliminary works were started in 1979 by the erstwhile UPSEB along with UP Irrigation Department and the main civil works contracts were signed in the years from 1980-84. The original estimate of the project (with an installed capacity of 3x52 MW), costing Rs. 4333.00 Lakhs, was submitted to CWPC in April 1972. The cost was updated to Rs. 4571.00 L
akhs during examination by CWPC in June, 1973. This cost was cleared by CWPC. The project installed capacity was then revised to 4x76 MW due to revision in design discharge of HRT from 120 cumecs to 142 cumecs.The civil works on the project at Diversion dam and tunnel were taken up but the pace was slow due paucity of funds and geological hurdles. The works finally came to a halt in 1990-91 due to non availability of funds. By then 9 km of tunnel had been excavated and works of barrage complex were in advance stage of completion. The orders for the Generating equipment of the power stations had also been placed with M/s B.H.E.L. and an expenditure of Rs.153 crores had been made on the project. Subsequently, Government of UP made efforts to get the project completed in private sector or through Central Sector undertakings viz. NHPC, THDC etc. but could not succeed in making headway. The project estimate was revised on 2/99 price base for Rs. 1249.18 crores (including escalation and IDC) and techno-economic clearance was accorded by CEA vide their letter number F.No. 2/UP/46/99-PFC/1298-1321 dated 21.2.2000.

Revival of the Project after formation of Uttaranchal

After the formation of Uttaranchal on 9.11. 2000 and Uttaranchal Jal Vidyut Nigam Ltd. (UJVNL) on 9.11.2001, a decision was taken to revive the project to unlock the investments on the project (Rs 165 crores up to 10/2002) and derive benefit of power generation. Financial Assistance for the project was taken from Power Finance Corporation(PFC). Now, on 1/2005 price base, a revised estimate of Rs. 1714.41 crores have been submitted to CEA, New Delhi for approval.
The restart of the project was a major challenge requiring financial intermediation, revival of old civil work contracts and detailed inspection of the half completed works which might have seen the aging effect and deterioration during the long idle period. The earlier civil work contracts were revived and considerable renovation work of infrastructure like roads, buildings and other facilities had also been done.
The MOU between UJVNL and Irrigation Department was signed on 25.06.2002. and the major works were started in October 2002. The project was slated for commissioning in Octobet 2005. 

Due to non-completion of the civil works, the revised schedule of commissioning of project
is now March 2007.

Salient features of the project

1. 81 meter long barrage with a storage capacity of 7.55 lac cum., with intake and sedimentation tank near the barrage. The barrage will provide a daily peaking of about four hours during the lean season . 

2. 16 km long, 6.0 m diameter horse shoe shaped head race tunnel from Diversion barrage to power house with 172 m high, restricted orifice type surge tank, of 13.7 m diameter, at the end of the head race tunnel.

3. Four steel penstocks of 3.0 m diameter.
 
4. A surface power station of 4 units of 76 MW (BHEL make) with Francis turbines along with a 220 kV switchyard.

5. Annual generation of 1566GWh.

The power from the project shall be evacuated to Rishikesh sub-station through three 220 kV lines. Two lines, which are already evacuating power to Rishikesh from Maneri Bhali Stage-I, are to be looped in and out at this switchyard. The third line is being constructed by Power Transmission Corporation of Uttaranchal Ltd.(PTCUL), wing of Uttaranchal Power Corporation. Foundation work of 156 out of 216 tower locations has been completed and 148 tower have been erected. Case for the clearance of forest land for 65 tower has been submitted in M.O.E.F., whose team has visited the site, the clearance is awaited.  

Technology Assimilation

Efforts have been made to adopt the state of art technology during construction and operation and to provide best possible protection to the machines based on the past experience. Also to provide flexibility during operation and maintenance some features have been provided. Some of the major features are given below:
  
1. The governors and excitation system for the machines in the power station are microprocessor based and numeric relays are being provided in protection system.

2. Sedimentation chamber has been designed to exclude silt particles larger then 150 microns.

3. High Velocity Oxy Fuel (Tungsten Carbide) coating would be provided on under water parts of the machines to prevent erosion due to silt in river Bhagirathi containing very high percentage of quartz.

4. Facility to remove of runner from the bottom to facilitate faster replacement of runners and to avoid long outage of machines.

5. Single phase main transformers to reduce the transportation weight/ dimensions.
 
6. Nitrogen based fire protection system for transformers.

7. Unit penstocks with penstock protection valves to facilitate isolation of individual penstocks/ machines for maintenance and to avoid loss of generation.

8. Use of cyclonic strainers in cooling water system for machines to provide efficient filtration of water, good quality of cooling water and longer life to coolers.

Till 30/11/2006, 94.49% work of the project is completed. All the E & M works will get completed by the end of January 2007. 

With the completion of project in March 2007,  UJVNL would be able to generate another  1,566 million units of energy (on 90% dependable discharge) in a year to the state of Uttaranchal. The project would also provide 4 hours of storage during lean season to provide high value peaking power.


Associated Sites | Site Map | Feedback & Queries  |  Contact us  | Home

© 2006 Uttaranchal Jal Vidyut Nigam Limited All rights Reserved