O&M Expenses

1. O&M Expenses projected by UJVNL take into consideration a combination of reasonable and measurable factors.

I) Adequate M & R to bring generating units back to nameplate capacity

           (a) Relining of power channels at Dhakrani & Dhalipur Stations.

II) Cost for employing “Rajya Raksha Vahini” / UPSUL as per GoU orders.

III) Employee terminal liabilities that were hitherto not provided for.

IV) Additional expenses that were not being provided for previously:

           (a) Concessional Electricity facilities for Irrigation Department personnel. 
           (b) Uniforms & Safety equipment for employees of both ID & UJVNL.
           (c) Regulatory expenses including the fees paid to the UERC.
           (d) Cost of distribution of electricity to various colonies.
           (e) Repair of buildings and roads in the plants, valley headquarters.
           (f) Salaries & facilities of ID employees working on UJVNL Projects.

2. Even the CERC norms permit petitioners to separately ask for additional expenses that are peculiar to the generating conditions & plants, in particular old plants.

O&M Expenses
O & M Expenses as projected by UJVNL
(in Rs Cr)  Dhakrani  Dhalipur  Chibro  Khodri  kulhal Ramganga  Chila  MBhali  Khatima
Projected Base Expenses for
FY05
16.22 13.97 27.10 14.33 6.00 12.07 17.32 16.94 6.46
Expenses Incurred by Other Deptts.
Irrigation Department 0.80 1.25 3.06 1.65 0.72 1.76 2.74 2.42 0.88
Employee Benefits 0.05 0.08 0.20 0.11 0.05 0.12 0.18 0.16 0.06
Total O & M Expenses in FY05 17.08 15.30 30.37 16.09 6.76 13.94 20.24 19.52 7.40
UPCL's Share of O & M
  Expenses 
12.81 11.47 22.78 12.07 5.41 13.94 20.24 19.52 7.40

O & M Expenses projected as per UERC Regulations
(in Rs. Cr)  Dhakrani  Dhalipur  Chibro  Khodri  Kulhal Ramganga  Chila  MBhali  Khatima
Actual Expenses for FY03 3.46 5.36 13.19 7.10 3.08  7.57 11.80 10.42 3.81
Actual Expenses for FY04 4.23 6.56 18.60 8.18 3.77 8.90 11.83 10.25 3.61
Average of Expenses for
FY03 & Fy04
3.84 5.95 15.89 7.64 3.43 8.24 11.81 10.34 3.71
Projected Base Expenses for FY05 4.08 6.31 16.86 8.11 3.63 8.73 12.53 10.96 3.93
Expenses Incurred by Other Deptts.
Irrigation Department 0.80 1.25 3.06 1.65 0.72 1.76 2.74 2.42 0.88
Employee Benefits 0.05 0.08 0.20 0.11 0.05 0.12 0.18 0.16 0.06
Total O & M Expenses in FY05 4.93 7.64 20.12 9.86 4.40 10.61 15.45 13.54 4.88
UPCL's Share of O & M 
 Expense
3.70 5.73 15.09 7.40 3.52 10.61 15.45 13.54 4.88